    When to raise a change control

    Our managed service contract is due for renewal - should we raise the change control now - or wait until the contract has been awarded and we know which company have won the tender?

  2. #2
    Forum Member
    Join Date
    Nov 2016
    Posts
    36
    I would raise a change as soon as possible, to ensure you are consulted during the tender process, particularly if there is a risk that specific requirements of the transfusion department may be overlooked.